'Absolutely stunning': New $825m highway nears completion

Author
RNZ,
Publish Date
Fri, 9 May 2025, 2:34pm
The four-lane highway snakes through hills and between wind turbines. Photo / RNZ
The four-lane highway snakes through hills and between wind turbines. Photo / RNZ

'Absolutely stunning': New $825m highway nears completion

Author
RNZ,
Publish Date
Fri, 9 May 2025, 2:34pm

Most of the tarseal is down, many of the barriers are up and there鈥檚 fresh paint lining the route. 

The long-awaited new road connecting the lower North Island鈥檚 eastern and western sides is just weeks away from opening. 

The views from the lower slopes of the Ruahine Range are breathtaking, as RNZ experienced on a drive over the four-lane Te Ahu a Turanga 鈥 Manawat奴 Tararua Highway on Thursday. 

We started at the Ashhurst, Manawat奴, end, beginning about where the old State Highway 3 through the Manawat奴 Gorge ran, before crossing the Manawat奴 River on the first of two viaducts and then entering a steep climb. 

The old State Highway 3 is visible to the right, and the 2011-12 slip has left a clear scar. Photo / RNZThe old State Highway 3 is visible to the right, and the 2011-12 slip has left a clear scar. Photo / RNZ 

The road will open in June, on a date not yet set. 

Tour guide and NZ Transport Agency project spokesman Grant Kauri said the views on the road were amazing, including the peak through the gorge when starting out. 

鈥淵ou can see the old Manawat奴 Gorge road, with Ruahine and Tararua maunga and the Manawat奴 River in the background. It鈥檚 absolutely stunning.鈥 

Clearly visible is the slip that closed the road through the gorge for a year in 2011-12, five years before more slips closed it for good. 

In 2021 construction began on the new $825 million highway. It鈥檚 expected the 11.5km route will take less than 15 minutes to drive, a big improvement on the windy and slow alternative routes in use for the past eight years. 

鈥淲e鈥檙e going up a 9.5% grade over a stretch of about 3km. In terms of context and what the fuel will be like it鈥檚 similar to Transmission Gully,鈥 Kauri said as we climbed towards the road鈥檚 summit. 

It鈥檚 actually slightly steeper than that highway, north of Wellington. 

As we head towards Woodville, through the wind turbines, the road here looks pretty well ready to use. 

鈥淎long the main alignment itself [we鈥檙e] finishing off the final surface of the asphalt, followed by the line marking and the median barrier installation,鈥 Kauri said. 

鈥淲e still have a number of works open off the main alignment itself.鈥 

Grant Kauri says working on the new highway is a career highlight. Photo / RNZGrant Kauri says working on the new highway is a career highlight. Photo / RNZ 

Some of that is on the new walking and cycling track that snakes along near the road. 

At the summit, as the road carves through the hills, Kauri said ground conditions were challenging because of how wet it was. 

So, the road builders got rid of the unstable material, replaced it with something better and compacted it. 

There are about 300 workers still onsite and some would remain after the road opened, completing tasks such as drainage and planting. 

As the road drops towards Woodville, at the Tararua end, the slope isn鈥檛 quite as steep. 

Unlike the old gorge road, on the unstable northern Tararua Range, ground conditions here mean slips are unlikely. 

Kauri said working on the project was a career highlight 鈥 something he never envisaged when he began in the industry and used to work on the old road. 

鈥淚n my former life I was responsible for clearing some of the slips in the Manawat奴 Gorge. I remember some of the late callouts in the middle of the night 鈥 raining, windy.鈥 

Covid, Cyclone Gabrielle and challenging ground conditions were the toughest parts of this road build, he said. 

- Jimmy Ellingham, RNZ 